Current Projects

Information will be forwarded to impacted residents prior to the start of construction concerning schedules and other project related information. Sign up for email updates at desplainesil.gov/construction or contact the designated Resident Engineer with questions.

Learn more about the Capital Improvement Program here.

2025 CIP Water Main Improvements, Contract A; Start Summer 2025

Point of Contact/Resident Engineer: Eric Heiker, P.E., 847-391-5617 or eheiker@desplainesil.gov.

Location
Limits
Improvements
Douglas Av Howard Ave To South Dead End
8" Water Main; Street Reconstruction
Prospect Av Lee St To Illinois St 8" Water Main; Street Rehabilitation
Sixth Av Greenview Ave To Prairie Ave 8" Water Main; Street Rehabilitation

 

2026 CIP Water Main Improvements, Contract A; Start Spring/Summer 2026

Point of Contact/Resident Engineer: Eric Heiker, PE, 847-391-5617 or eheiker@desplainesil.gov.

Location
Limits
Improvement
Birch St Touhy Ave to Dead End North 8" Water Main; Street Reconstruction
Fifth Ave Algonquin Rd to Forest Ave 8" Water Main; Street Rehabilitation
Prairie Ave Fifth Ave to Second Ave 8" Water Main; Street Reconstruction

 

2026 CIP Street Improvements, MFT 26-00232-00-RS; Start Summer 2026

Point of Contact/Resident Engineer: Becka Shipp, PE, 847-391-5388 or bshipp@desplainesil.gov.

Location
Limits
Improvement
Berkshire Ln Albany to Marcella Resurface
Berkshire Ln Marcella to Dead End Resurface
Birchwood Ave Cedar to Dead End Resurface
Brown St Laurel to Western Resurface
Chase Ave Magnolia to Scott  Resurface
Fourth Ave Lincoln to Forest Ave Resurface
Fremont Ave Mr. Prospect to Lasalle   Resurface
Kinkaid Ct Marshall to Arnold  Resurface
Kylemore Ct Kylemore to Dead End  Resurface
Kylemore Dr Lismore to Carlow Resurface
Kylemore Dr
Wexford to Lismore
Resurface
Kylemore Dr
Wolf to Wexford
Resurface
Oakton Pl Oakton to Dead End Resurface
Redeker Rd Des Plaines River Rd to Dead End
Resurface
Shawn Ln
Ambleside to Lance
Resurface
Third Ave Oakwood to Thacker Resurface
Walnut Ave Willson to Marshall
Resurface
Wexford Ct Kylemore to Dead End
Resurface
White St Algonquin to Ashland  Resurface 

 

2026 CIP Concrete Program, 26-00000-01-GM; Start Summer 2026

Point of Contact/Resident Engineer: Daniel Koltys, EIT, 847-391-5390 or dkoltys@desplainesil.gov.

Location
Limits
Improvement
Graceland/Lee Thacker St to Oakwood Ave Alley Improvements

When Will My Road be Repaired? 

Learn more about the City's Capital Improvement Program for road and alley work. The table lists the road, project type and year. For questions, contact our Engineering team at 847-391-5390 or by email.

Please note all projects are subject to funding and City Council approval. 

Frequently Asked Questions